South Park Township

Allegheny County, Pennsylvania. Status: Proposed Ordinance.

Skip the map

A proposed amendment to the South Park Township Zoning Ordinance would define data centers, including cryptocurrency mining, and allow them and their accessory uses as a conditional use in the I-1 Light Industrial and I-2 General Industrial Districts, with a 100-foot setback from properties with sensitive receptors, a 45-foot height limit plus 20 feet for rooftop equipment, a 50 percent lot coverage cap, off-hours noise limits of 65 dB (55 dB next to sensitive receptors), water and energy studies, and a 110 percent decommissioning bond updated every year. The September 11, 2026 draft was posted with the Planning Commission's October 28, 2026 agenda for a recommendation, and the Board of Supervisors had rescheduled its public hearing to November 9, 2026.

Status
Proposed Ordinance
County
Allegheny County
Rating
Draft: 7 of 10 Core Protections addressed (Broad coverage), 1 at the strongest standard, 39 of 104 points
Where data centers are allowed
Proposed conditional use in the I-1 and I-2 districts
Ordinance
None Adopted
Last verified
November 4, 2026

Key Milestones

  • October 28, 2026: A Planning Commission meeting was scheduled at 7:00 p.m. with the data center zoning amendment on the agenda for a motion to recommend, not recommend, or table it, and the posted agenda attached the September 11, 2026 draft ordinance. No outcome has been posted.
  • October 23, 2026: The township took a 30-day extension on a Right-to-Know request for the draft, with a response expected by November 22, 2026.
  • October 19, 2026: The township Open Records Officer said the draft must be requested through a Right-to-Know request.
  • October 19, 2026: A Right-to-Know request for the current draft of the zoning amendment allowing data centers as a conditional use in the I-1 and I-2 districts and the notice for the public hearing rescheduled to November 9, 2026 was emailed to the township.
  • October 12, 2026: The Board of Supervisors agenda for this meeting included no data center item.

Sources

See every Allegheny County municipality

Submit a Correction

Tell us what is out of date or incorrect, or send a new draft. A link to a supporting document, such as an ordinance or meeting minutes, helps us confirm the change. Corrections are reviewed within 30 days, and those tied to an upcoming hearing or vote are reviewed first.