Ordinance Builder

Everything an official or resident needs to write, strengthen, and evaluate a data center ordinance.

How Ratings Work

Use this page to understand how the tracker rates an ordinance and what each score means.

  • Quick Check

    Ten Core Protections

    Ten Core Protections
    What it asks
    Does the ordinance include the ten protections residents care about most?
    How it is scored
    Each protection is Strongest Standard, Basic Standard, or Not Addressed. The score is how many of the ten it includes, such as 6 of 10.
    What you see
    The overall coverage rating (Broad, Partial, Narrow, or No coverage) on the map and at the top of every municipality and county page.
    How the ten are rated
  • Full Assessment

    Category Scorecard

    Category Scorecard
    What it asks
    How thoroughly does the ordinance cover every topic, including traffic, lighting, and emergency planning?
    How it is scored
    All 52 criteria earn 0, 1, or 2 points, for a total of 104, grouped into eight categories.
    What you see
    A level for each category (Strong, Moderate, Weak, or None) and the total points on each municipality page.
    See all 52 criteria

Review Process

An ordinance is rated only from its full text, and every rating is reviewed by the tracker's maintainer before it is published. Where the text could not be read, the entry shows Rating Pending. Proposed ordinances are rated from the posted draft and are labeled as drafts. A municipality whose zoning has no data center rules has 0 of 10 Core Protections, with every protection Not Addressed.

Ten Core Protections

These ten protections reflect the concerns residents raise most often in polls and at Pennsylvania hearings.

Select a card to turn it over and read what the protection requires.

  • Protection 1

    Expansion Limits

    Expansion Limits

    Requires a new approval before a data center adds buildings, generators, cooling, batteries, substations, or power demand beyond what was approved.

  • Protection 2

    Water Supply

    Water Supply

    Requires public water for cooling where it is available, and a well study before any groundwater is used.

  • Protection 3

    Cooling Method

    Cooling Method

    Requires water-saving cooling, such as closed-loop systems.

  • Protection 4

    Generator and Air Limits

    Generator and Air Limits

    Limits backup diesel generator testing and air emissions.

  • Protection 5

    Noise Limit

    Noise Limit

    Caps how loud a data center can be at the property line, as a fixed limit or as an increase over the measured background sound.

  • Protection 6

    Low-Frequency Noise

    Low-Frequency Noise

    Addresses the low hum from cooling fans and equipment.

  • Protection 7

    Public Transparency

    Public Transparency

    Requires the developer, operator, and end user (or a binding operating profile) to be named, and limits non-disclosure agreements with officials.

  • Protection 8

    Farmland Protection

    Farmland Protection

    Keeps data centers off preserved farmland and protects prime farm soils in the districts where they are allowed.

  • Protection 9

    Home Setback

    Home Setback

    Requires a safe distance between nearby homes and a data center, including its outdoor equipment.

  • Protection 10

    Decommissioning

    Decommissioning and Reuse

    Requires money set aside to remove equipment, fuel, and batteries if the facility closes, and reuse or removal of the building.

Rating Levels

Each of the ten protections is rated at one of three levels.

StrongestStrongest StandardMatches the strongest rule adopted by at least two Pennsylvania municipalities. Counts toward the score.
BasicBasic StandardSets a specific rule, but a weaker one. Counts toward the score.
NoneNot AddressedSays nothing about it. Does not count.

Coverage Scale

The score is the number of protections addressed at either standard, out of ten.

Broad7 to 10Broad CoverageThe ordinance addresses seven to ten of the protections.
Partial4 to 6Partial CoverageThe ordinance addresses four to six of the protections.
Narrow1 to 3Narrow CoverageThe ordinance addresses one to three of the protections.
None0No CoverageThe ordinance addresses none of the protections.
Keep In Mind

Coverage counts how many topics an ordinance addresses, not how protective each provision is.

Electricity rates are set by the Pennsylvania Public Utility Commission or by an electric cooperative board, so grid costs are rated as a disclosure requirement and not as a Core Protection.

Category Scorecard

The Category Scorecard rates an ordinance on all 52 criteria, grouped into eight categories. Each criterion earns 0, 1, or 2 points, for a total of 104, and each category receives one of four levels.

Category Levels

StrongAt least two-thirdsThe ordinance earns at least two-thirds of the category’s points.
ModerateOne-third to two-thirdsThe ordinance earns between one-third and two-thirds of the points.
WeakLess than one-thirdThe ordinance earns some points, but less than one-third.
NoneNo pointsThe ordinance does not address the category at all.

Eight Categories

Land Use11 criteria, 22 points
Noise6 criteria, 12 points
Environment8 criteria, 16 points
Energy6 criteria, 12 points
Visual Character5 criteria, 10 points
Safety4 criteria, 8 points
Traffic3 criteria, 6 points
Accountability9 criteria, 18 points

Scoring Rules

  • Ratings come only from the full ordinance text: the zoning ordinance, its amendments, and any other adopted ordinance that applies to data centers.
  • An ordinance that meets only part of a multi-part 2-point standard earns 1 point.
  • A general rule that applies to all uses earns points only if the ordinance says it applies to data centers.
  • Criteria 51 and 52 may be met by any adopted ordinance, resolution, or policy.
Keep In Mind

The 104-point total is reported as a number only. The overall coverage rating always comes from the Core Protections count, and these levels describe a whole category, not a single protection.

All 52 Criteria

Each criterion earns 2 points, 1 point, or 0 points, for a total of 104. An ordinance that falls short of the 1-point standard earns 0 points for that criterion.

Select a category to open its book of criteria.

View All 52 Criteria As A List

Land Use: Criteria 1 to 11

#Criterion2 Points1 Point
1District LimitsAllowed only in named districts or in an overlay mapped when the ordinance is adopted, and expressly excluded from all other districts.Limited to named districts or an overlay, but the exclusion elsewhere is not stated or the overlay is not mapped.
2Approval ProcessConditional use heard by the governing body, and approval lapses if the land development plan is not filed or construction does not begin within stated periods.Special exception by the Zoning Hearing Board, or a conditional use with no lapse provision.
3Agricultural LandBarred on land under an agricultural conservation easement, plus a standard limiting disturbance of prime agricultural soils in the districts where data centers are allowed.Barred on preserved farmland only, or barred in agricultural districts.
4Minimum Lot Size30 acres or more.Any smaller minimum.
5Maximum ScaleCampus-wide cap on the total footprint of buildings and outdoor equipment, or on electrical demand in megawatts.Per-building cap or lot coverage cap only.
6Residential Setback1,000 ft or more from homes or residential districts, or a setback scaled to building size or modeled noise with a floor of at least 500 ft, measured from buildings and all outdoor equipment.100 to 999 ft, or a larger distance measured from the main building only.
7Sensitive-Use SetbacksAt least 1,000 ft from schools, day care centers, hospitals, and parks.A smaller distance, or only some of these uses protected.
8HeightHeight limit no greater than the district limit for other principal buildings, with rooftop equipment counted in the height or limited to 10 ft above the roof and screened.A height limit that exempts rooftop equipment.
9Natural ResourcesRiparian buffer of at least 100 ft on each side of streams, wider on steep slopes and at wetlands, in the data center provisions or in a general ordinance they expressly apply.Environmental impact assessment required, or base ordinance protections stated as applying.
10Data Center SeparationA campus on commonly controlled lots regulated as one use, plus a separation distance between campuses or a rule that performance limits apply to the combined output of nearby data centers.One of these.
11Expansion LimitsAny added building area, generators, cooling, battery, or substation capacity, or electrical demand above the approved level, requires a new approval, with like-for-like replacement exempt.Phasing plan stating the electrical demand of each phase, or expansion review without stated triggers.

Noise: Criteria 12 to 17

#Criterion2 Points1 Point
12Noise LimitsSeparate day and night limits of 50 dBA and 45 dBA or lower at the property line, or a cap of 5 dBA or less above measured background with a fixed nighttime ceiling, in either case with a stated measurement method.A single limit, higher limits, or limits with no stated method.
13Background CapNo more than 10 dBA above measured background (L90) by a stated method, with a floor below which the cap does not apply.A background cap above 10 dBA, or a cap with no stated method or floor.
14Low-Frequency NoiseNumeric low-frequency limits of 60 dBC day and 55 dBC night or lower, or octave-band limits at 31.5, 63, and 125 Hz.A higher dBC limit, or a low-frequency noise study only.
15Sound StudiesA predictive study with the application and a measured study at full operating load after opening, both by a stated method.A predictive study only, or studies with no stated method.
16Generator UseTesting only on weekdays in daytime hours, with a daily or annual hours cap that allows tests required by code.Daytime-only testing or an hours cap.
17VibrationA numeric vibration limit at the property line or receptor, with a stated measurement method and a vibration study.A general or perception-only vibration standard.

Environment: Criteria 18 to 25

#Criterion2 Points1 Point
18Water SupplyCooling water must come from available public water, and any on-site well requires a hydrogeologic study with pump tests.Water feasibility study required.
19Cooling MethodClosed-loop or other low-water cooling required, and any evaporative system limited to a stated water-use rate and shown to meet the noise limits.Cooling method and projected water use must be disclosed.
20Water UseMetered water use reported to the municipality, together with a drought plan tied to state, basin commission, or supplier drought declarations.One of these, or projected use disclosed.
21WastewaterCooling and process wastewater disposal route identified, with the applicant required to show approval by the Department of Environmental Protection, the Sewage Enforcement Officer, or the sewer authority.A general wastewater plan, or approvals that may wait until the building permit.
22StormwaterAdded treatment and spill containment for runoff from fuel, generator, and transformer areas, beyond the base stormwater ordinance.Base ordinance standards stated as applying.
23Air EmissionsGenerators must meet EPA Tier 4 Final emission levels or equivalent, with annual emissions testing or reports.Generators must meet state and federal emission rules.
24Waste HeatThermal plan with modeled property line temperature effects and a heat reuse evaluation.Heat impacts must be disclosed.
25Electronic WastePlan for on-site storage and removal of servers, batteries, and refrigerants, with a disposal contract kept in effect.General disposal requirement.

Energy: Criteria 26 to 31

#Criterion2 Points1 Point
26Power CapacityEvidence of a utility service request with the application, and the utility's written capacity confirmation or executed service agreement before a zoning permit.Utility letter required before a building permit.
27Energy PlanEnergy plan stating peak demand by phase, annual use, and design efficiency, plus rooftop solar on a set share of unused roof area or an incentive for on-site renewable generation.Energy plan required.
28On-Site Power PlantsOn-site generation for normal operation treated as a separate use with its own approval, setbacks, and noise and emission standards equal to those for other generation uses.On-site generation addressed.
29Substations and LinesApplicant-owned substations screened and placed to the side or rear, and applicant-owned on-site lines of 34.5 kV or less buried.Applicant-owned substations screened or counted as part of the use.
30Battery StorageBattery storage set back from property lines, homes, and wells, with large-scale fire test data, a hazard mitigation analysis, and a battery emergency plan shared with the fire company.Battery storage must comply with NFPA 855 and the fire code as adopted.
31Grid Cost DisclosureApplicant names its electric provider, discloses required grid upgrades, their estimated cost, and the tariff or cooperative policy terms that assign that cost, and files the executed service agreement before a zoning permit.Required upgrades must be disclosed.

Visual Character: Criteria 32 to 36

#Criterion2 Points1 Point
32BuffersPlanted buffer of 100 ft or more next to residential lots and districts, with year-round screening and replacement of dead plants.Smaller buffer.
33LightingFully shielded, with no light crossing the property line.Shielded, with or without a footcandle limit.
34Building DesignMeasurable facade standards for articulation, materials, and color on walls visible from roads or homes.General design language.
35Fencing and ScreeningAll ground and rooftop equipment screened on all sides to at least its own height, with sound walls or enclosures where needed to meet the noise limits.Equipment must be screened.
36ViewshedVisual impact study from public roads and historic sites, with renderings.Building elevations required.

Safety: Criteria 37 to 40

#Criterion2 Points1 Point
37Emergency PlanPlan accepted by a municipal official after fire company review, updated every year, with an annual site walk-through offered to responders and posted 24-hour contacts.Emergency plan required.
38First RespondersApplicant delivers site-specific responder training before occupancy and every year, and keeps on site any specialized equipment the emergency plan identifies, at no cost to responders.Applicant must coordinate training.
39Hazardous MaterialsBulk fuel and hazardous material storage set back from property lines, wells, and streams, with containment meeting state and federal rules and a spill response plan filed with the municipality.Hazardous materials must be disclosed, or storage setbacks or containment only.
40InspectionsAnnual fire safety inspection with a report to the municipal fire official, and deficiencies corrected within a set time.An inspection at opening only, or annual inspections without a report.

Traffic: Criteria 41 to 43

#Criterion2 Points1 Point
41TrafficTraffic impact study in every case, covering construction and operation and reaching the nearest arterial or interchange the trucks will use.Study above a size threshold, or covering operation only.
42Road AccessArterial or collector road access and a secondary emergency access.One of these.
43Construction ImpactsConstruction days and hours, haul routes on municipal roads, and road security through posting and an excess maintenance agreement or bond.Some of these.

Accountability: Criteria 44 to 52

#Criterion2 Points1 Point
44Decommissioning and ReuseRecorded agreement with security of at least 110% of removal cost; fuel, batteries, generators, and outdoor equipment removed within 6 months of abandonment; and buildings removed unless lawfully reused within 2 years.Agreement or plan without financial security.
45Cost UpdatesEstimate updated after the first year and at least every 5 years, with security adjusted to match.Updated at least every 10 years or at transfer of ownership.
46Definition ScopeDefinition covers cryptocurrency mining and artificial intelligence or high-intensity computing regardless of technology, with an exemption for accessory computer rooms below a stated size or power.One of these.
47Compliance ReportingOngoing reports on noise, water, or power use.One report after opening.
48EnforcementStated grounds for suspension or revocation after notice and a hearing, together with enforcement under Sections 616.1 and 617.2 of the Municipalities Planning Code.General enforcement provision, or penalties without stated revocation grounds.
49Independent ReviewApplicant pays reasonable fees for the municipality's consultants to review its studies in land development review.Independent review allowed, cost not assigned.
50Public EngagementApplicant community meeting before planning commission review and a project website kept current through final approval.One of these, or an extended comment period.
51Confidentiality AgreementsOfficials, staff, and consultants barred from signing NDAs with data center applicants, by ordinance, resolution, or written policy.NDAs allowed but must be disclosed and approved at a public meeting.
52Applicant DisclosureApplicant names the developer, operator, and end user before approval, or files a binding worst-case operating profile and names the end user before occupancy.Applicant must name developer or operator.

Status Definitions

Whether a municipality has data center rules at all is shown by its status, not by either rating. The ratings describe how strong the rules are.

Adopted OrdinanceThe municipality’s own governing body has enacted, by ordinance, rules that regulate data centers. An ordinance that adopts county standards by reference counts; a resolution does not.
County Rules ApplyThe municipality has no data center rules of its own, and a county ordinance reaches it by its own terms. Most often this is a county subdivision and land development ordinance, which the Municipalities Planning Code applies in every municipality that has not adopted its own. The rating shown is the county ordinance’s rating.
County Rules May ApplyA county ordinance exists, but the municipality has, or may have, its own zoning or subdivision ordinance, and the county ordinance states no authority that reaches it. Each municipality’s page explains why the reach is uncertain.
Proposed OrdinanceThe municipality is considering data center rules.
No OrdinanceThe municipality has neither adopted nor proposed data center rules.
Keep In Mind

Counts of adopted ordinances, and each county’s typical rating and highest rated ordinance, include only the municipalities’ own ordinances, so one county ordinance is not counted dozens of times. County rule coverage is reported beside them, for example on the home page and the For Reporters page.

Public Access

Every entry with an adopted or proposed ordinance also records whether residents can read the ordinance online. Public Access is reported separately and does not change the Core Protections count.

AvailableThe current ordinance and every amendment, including drafts under review, are posted online as searchable text. Residents can also request a copy in person or by mail.
LimitedThe online copy is missing, out of date, incomplete, or posted only as a scan. Residents can request a copy from the municipal office in person or by mail.
Keep In Mind

Municipalities with no data center ordinance show "No ordinance" instead, since there is nothing to post.

Changes To The Standard

Tracker Standard version 2.0 (October 29, 2026). After a legal review of all 52 criteria, the standard now rewards the most defensible rule rather than the largest number, and every rated ordinance was rescored.

Expansion Limits replaced Grid Cost Protection as a Core Protection, because Pennsylvania municipalities have no power to decide who pays for grid upgrades. Noise limits tied to the measured background now earn full credit, decommissioning allows reuse of the building, and requirements tied to state permits count when written as conditions of approval. Every rated ordinance was rescored under version 2.0. Where a stricter test could not be confirmed from the recorded evidence, the earlier score stands until the ordinance text is reread.

On October 28, 2026, the protection labels Strongest Standard, Basic Standard and Not Addressed replaced Strong, Moderate, Weak and None; the numbers and colors did not change. On November 4, 2026, a category that earns no points was relabeled None, so that Not Addressed is used only for the ten protections.

Terms used on this page are defined in the Glossary.

Strengthen an Ordinance

The Ordinance Builder sets a standard for each of these 52 criteria, shows which Pennsylvania municipalities already adopted it, and drafts an ordinance for your solicitor.

Open the Ordinance Builder

Glossary

Use this list to look up the zoning terms used on this site, explained in plain language.

27 terms

Ways a Data Center Can Be Approved

How an ordinance lets a data center in, from the least review to the most.

Permitted by Right
A use that is allowed without a hearing, as long as the project meets the written standards in the ordinance.
Conditional Use
A use the zoning ordinance allows only after the elected governing body, such as the supervisors, commissioners, or council, holds a public hearing and finds that every condition in the ordinance is met. Residents may testify at the hearing.
Special Exception
A use the zoning ordinance allows only after the Zoning Hearing Board holds a public hearing and finds that every condition in the ordinance is met. Residents may testify at the hearing.
Variance
Permission from the Zoning Hearing Board to depart from a zoning requirement because of a hardship unique to the property.

Changing the Rules

The steps a township, borough, or city takes to add or change data center rules.

Zoning Amendment
A change to the text of the zoning ordinance or to the zoning map. It follows the same review, hearing, and vote steps as a new ordinance.
Rezoning
Changing the zoning district of particular parcels on the zoning map, for example from agricultural to industrial.
Overlay District
An area drawn on top of the regular zoning map that adds rules for one kind of use, such as data centers, only on the mapped parcels.
Curative Amendment
A process under the Pennsylvania Municipalities Planning Code for fixing part of a zoning ordinance that is claimed to be invalid. When a municipality starts one itself, it has 180 days to adopt the fix, and challenges to that part are put on hold.
Moratorium
A temporary hold on accepting or approving certain applications while the municipality writes new rules.
First Reading
The first time a city or borough council formally reads a proposed ordinance. A final vote usually comes at a later meeting.
Public Hearing
A meeting advertised in advance where anyone may speak or submit comments before officials decide. Pennsylvania law requires one before a zoning ordinance or amendment is adopted.

Boards and Plans

The bodies and documents that shape local land use decisions.

Planning Commission
An appointed advisory body that reviews proposed zoning changes and development plans and recommends what the elected governing body should do. It does not adopt ordinances.
Zoning Hearing Board
An appointed board that decides special exceptions, variances, and appeals of the zoning officer's decisions, after a public hearing.
Comprehensive Plan
A municipality's long-range plan for land use. Zoning is supposed to carry out the plan, but the plan itself does not regulate any property.
SALDO
The Subdivision and Land Development Ordinance, which sets the rules for dividing land and for site plans, such as roads, stormwater, and landscaping.

Standards in an Ordinance

Terms that appear in the protections an ordinance sets.

Setback
The minimum distance a building or piece of equipment must be from a property line, a home, or another feature.
dBA
A measure of sound level weighted to match how people hear. Lower numbers are quieter; a 10 dBA increase sounds about twice as loud.
dBC
A measure of sound level that gives more weight to low-frequency sound, such as the hum of cooling equipment, which dBA limits can miss.
Battery Energy Storage System
Large batteries that store electricity on site, often used for backup power at data centers.
Decommissioning
Removing a facility and restoring the site when it closes. A decommissioning bond is money the owner sets aside so the municipality can do the work if the owner does not.
Sensitive Receptor
A place where people are especially affected by noise or pollution, such as a home, school, hospital, nursing home, park, or place of worship. Ordinances often measure setbacks and noise limits from the nearest sensitive receptor.
Tier 4
The strictest federal emission standard for new diesel engines, including backup generators. Tier 4 engines release far less soot and nitrogen oxides than older engines.
Closed-Loop Cooling
A cooling system that circulates the same water or coolant in sealed pipes and needs only small top-ups, instead of drawing large amounts of water and evaporating it.

Rights, Records, and Appeals

How residents get information and challenge decisions.

Right-to-Know Request
A written request for public records under Pennsylvania's Right-to-Know Law. The municipality must respond within five business days or say it needs up to 30 more days, and a denial can be appealed to the Office of Open Records.
Nondisclosure Agreement
An agreement in which officials promise to keep information about a project, such as the developer's or end user's name, confidential. Some ordinances require that any such agreement be disclosed to the public.
Exclusionary Zoning
Zoning that leaves no reasonable place in a municipality for a lawful use. Pennsylvania courts can strike down such zoning, often after a developer files a curative amendment or a validity challenge.
Land Use Appeal
An appeal of a zoning or land use decision to the county Court of Common Pleas. Applicants and residents recognized as parties at the hearing generally have 30 days after the written decision to file.