Big Beaver Borough
Beaver County, Pennsylvania. Status: Adopted Ordinance.
Big Beaver Borough permits data centers with special regulations only in the Industrial district, on a tract of at least 50 acres with arterial or collector road access, public water and sewer, 100 foot setbacks from tract lines, and a 75 dBA noise limit at tract lines. The current rules are in Zoning Ordinance 245, which was enacted on October 15, 2024 and amended most recently on September 16, 2025, and the October 20, 2026 Council agenda listed a motion to adopt Ordinance 250 amending it, although no posted record yet confirms the vote. According to the Beaver County Office of Planning and Redevelopment, the county sent its comment letter on Ordinance 250 in late October 2026 and had not been told of its adoption as of November 10, 2026.
- Status
- Adopted Ordinance
- County
- Beaver County
- Rating
- 4 of 10 Core Protections addressed (Partial coverage), 1 at the strongest standard, 18 of 104 points
- Where data centers are allowed
- Permitted with special regulations in the Industrial district
- Ordinance
- No. 245; Ordinance 250 Passed, Signed Copy Pending
- Last verified
- November 19, 2026
Key Milestones
- December 18, 2026: This is the extended deadline for Council to decide the Switch preliminary land development application.
- November 15, 2026: The Borough Secretary reported by email that Council passed Ordinance 250 and that a signed copy is not yet available.
- October 20, 2026: The Council agenda listed a motion to adopt Ordinance 250, a motion to submit a curative amendment ordinance to the borough and county planning commissions, and a motion to advertise a December 1, 2026 public hearing on it.
- October 20, 2026: The Beaver County Planning Commission agenda listed a Big Beaver Borough zoning ordinance amendment and the revised Switch preliminary land development plans for review.
- October 11, 2026: The borough engineer issued a review letter on the Switch preliminary plans for three data center buildings of 215,750 square feet each, finding the tract size, utility, setback, and height standards met and the acoustics, spill plan, lighting, and buffer items still open.