Maidencreek Township
Berks County, Pennsylvania. Status: Proposed Ordinance.
Maidencreek Township's proposed zoning amendment would allow data centers only as a conditional use in its Industrial zoning district, with a 5-acre minimum lot, a 60-foot height limit, a 1,000-foot setback from sensitive receptors and residential districts that may be reduced to 500 feet, a 55 dBA limit at any lot line, a closed-loop water system with connection to public water and sewer, rooftop solar on at least 65 percent of the main building roof, generator testing limited to 8 hours a month, and decommissioning within 12 months backed by financial security. The unnumbered August 2026 draft, which the Supervisors authorized the solicitor to prepare as an amendment on September 10, 2026, is scheduled for a public hearing at the Supervisors' regular meeting on November 12, 2026 at 6:00 p.m. at the Township Building.
- Status
- Proposed Ordinance
- County
- Berks County
- Rating
- Draft: 6 of 10 Core Protections addressed (Partial coverage), 0 at the strongest standard, 44 of 104 points
- Where data centers are allowed
- Proposed: conditional use in the I Industrial District
- Ordinance
- None Adopted
- Last verified
- October 31, 2026
Key Milestones
- November 12, 2026: A public hearing on the data center zoning amendment is scheduled at the Supervisors' regular meeting at 6:00 p.m. at the Township Building.
- October 13, 2026: The Berks County Planning Commission issued its review letter on the proposed data center zoning amendment, with comments for the township to consider.
- October 8, 2026: The Supervisors' agenda listed authorization to advertise the November 12, 2026 hearing on the data center zoning amendment, according to BerksConnect.
- September 10, 2026: The Supervisors voted unanimously to authorize the solicitor to prepare a zoning amendment defining data centers and allowing them by conditional use in the Industrial Zoning District.
- August 19, 2026: The Supervisors considered a resolution to adopt a joint comprehensive plan.
Sources
- Proposed data center zoning amendment, Data Center Draft Aug 2026 (Adobe Acrobat, linked from the hearing notice)
- Board of Supervisors page with notice of the November 12, 2026 hearing
- Supervisors minutes, September 10, 2026
- Supervisors minutes, August 13, 2026
- Maidencreek Zoning, § 220-111 Conditional uses (eCode360)
- Maidencreek Zoning, § 220-63 Performance standards (eCode360)
Search all 67 counties and 2,568 municipalities, or a village or mailing-address name.