Doylestown Township's curative amendment defines data centers and allows them only as a conditional use in the LI Light Industrial District, with a 60 foot height limit that includes rooftop equipment, a 100 foot setback from property lines, a 200 foot setback where a site abuts a residential area, closed-loop water cooling unless an alternative uses less water and energy, and pre- and post-construction noise and vibration studies. The Board of Supervisors began the curative amendment process on June 16, 2026 and voted to adopt the ordinance after a public hearing on October 27, 2026, according to the township's meeting video, and the adopted text and ordinance number have not yet been posted.

Status
Adopted Ordinance
County
Bucks County
Where data centers are allowed
Proposed: conditional use in the LI Light Industrial District
Ordinance
Adopted October 27, 2026 (Number Not Posted)
Last verified
October 29, 2026

Key Milestones

  • October 27, 2026: The Board of Supervisors held a public hearing and voted to adopt the data center ordinance, according to the township's video of the meeting, with no opposition heard.
  • October 20, 2026: The township open records officer said by email that the township does not release draft ordinances, that an adopted ordinance will be posted on the township website, and that the data center item is on the October 27, 2026 Board of Supervisors agenda.
  • October 7, 2026: The Bucks County Planning Commission reviewed the curative amendment.
  • September 28, 2026: The Planning Commission agenda listed the draft data center zoning ordinance amendment.
  • September 28, 2026: The township Planning Commission voted 5 to 0 to recommend that the Board of Supervisors adopt the data center ordinance as written, with a change to the ratepayer impact language.