Plumstead Township

Bucks County, Pennsylvania. Status: Adopted Ordinance.

Skip the map

Plumstead Township allows data centers only by conditional use in the LI Light Industrial and Q Quarry districts, on sites of at least 25 acres with buildings set back 200 feet from all property lines, no taller than 35 feet, and subject to the township noise limit of 46 dBA at residential or agricultural property lines. The rules are in Ordinance 2026-02, which the Board of Supervisors adopted on June 10, 2026 and sent back to the township and county planning commissions to fine-tune, and no revised amendment had been adopted or advertised as of the August 26, 2026 Board minutes.

Status
Adopted Ordinance
County
Bucks County
Rating
5 of 10 Core Protections addressed (Partial coverage), 0 at the strongest standard, 23 of 104 points
Where data centers are allowed
Conditional use in the LI Light Industrial and Q Quarry districts
Ordinance
No. 2026-02
Last verified
October 29, 2026

Key Milestones

  • June 25, 2026: The Planning Commission discussed revisions, including a decommissioning plan with escrow, well protection, new approval for a 10 percent increase in use, tonal noise, solar panels, cameras, and heat.
  • June 10, 2026: The Board of Supervisors held a public hearing and unanimously adopted Ordinance 2026-02, then by general consent sent it back to the township and county planning commissions to review and fine-tune.
  • June 3, 2026: The Bucks County Planning Commission reviewed the amendment.
  • May 20, 2026: The Bucks County Planning Commission received the data center amendment for review (BCPC #34-26-2).
  • May 14, 2026: The township published notice of a June 10, 2026 public hearing on an ordinance creating a data center use as a conditional use in the Q Quarry and LI Light Industrial districts.

Sources

See every Bucks County municipality

Submit a Correction

Tell us what is out of date or incorrect, or send a new draft. A link to a supporting document, such as an ordinance or meeting minutes, helps us confirm the change. Corrections are reviewed within 30 days, and those tied to an upcoming hearing or vote are reviewed first.