Banks Township
Carbon County, Pennsylvania. Status: No Ordinance.
Banks Township has a zoning ordinance, according to Times News reports that most township land is zoned conservation and that the supervisors renamed the township zoning officer in January 2025, but its text is not posted online, so whether it addresses data centers could not be confirmed. No proposed or adopted data center ordinance appears in the Carbon County Planning Commission minutes of July 21, 2026 and agendas for August through October 2026, and the county commissioners said on March 24, 2026 that they knew of no overlay or zoning change request in Banks Township, although NorthPoint Development has proposed a data center on its Tresckow Mountain land.
- Status
- No Ordinance
- County
- Carbon County
- Where data centers are allowed
- Not listed
- Ordinance
- None Found
- Last verified
- November 4, 2026
Key Milestones
- March 24, 2026: The Times News reported that the county commissioners, asked about the proposed data center in Banks Township, said they knew of no overlay or zoning change request there and that zoning decisions belong to the municipalities.
- February 11, 2026: The Times News reported that the supervisors created a township planning commission that would review projects, including an anticipated data center for which the developer had not yet submitted a proposal.
- October 1, 2025: The Times News reported that NorthPoint presented its data center plan at a community meeting in Tresckow and said it would seek a zoning overlay.
- August 20, 2025: The Times News reported that NorthPoint Development had acquired about 1,400 acres atop Tresckow Mountain in Banks and Packer Townships for a possible data center, and that most of the land is zoned conservation.
- January 10, 2025: The Times News reported that the supervisors renamed the township zoning officer at their reorganization meeting.
Sources
- Carbon County municipal directory (Banks Township entry)
- Times News, Data center possible on 1,400-acre property (August 20, 2025)
- Times News, Data center developer presents plan in Tresckow (October 1, 2025)
- Times News, Banks Twp. retains Nice as chairman (January 10, 2025)
- Times News, Banks Township to add planning commission (February 11, 2026)
- Times News, Carbon commissioners respond to data center questions (March 24, 2026)