Potter Township

Centre County, Pennsylvania. Status: Adopted Ordinance.

Skip the map

Potter Township allows data centers, including cryptocurrency and artificial intelligence facilities, only as a conditional use in the Planned Commercial-Industrial (PCI) District, with a 3-acre minimum lot, setbacks of 1,000 feet from residential districts and properties for hyperscale data centers or those over 200,000 square feet, noise limits of 65 decibels by day and 60 decibels at night at adjoining property lines, closed-loop liquid or water-free dry cooling only, no water wells, and an environmental impact assessment reviewed at the applicant's cost, and it bans surveillance data centers in every district. The rules are in Ordinance No. 2-2026, which the Board of Supervisors enacted on October 19, 2026, adding Section 220-83.A to the township zoning ordinance.

Status
Adopted Ordinance
County
Centre County
Rating
5 of 10 Core Protections addressed (Partial coverage), 2 at the strongest standard, 31 of 104 points
Where data centers are allowed
Conditional use in the PCI District
Ordinance
No. 2-2026
Last verified
October 29, 2026

Key Milestones

  • October 20, 2026: The township secretary provided a signed copy of Ordinance No. 2-2026 by email.
  • October 19, 2026: The Board of Supervisors adopted Ordinance No. 2-2026, allowing data centers only as a conditional use in the Planned Commercial-Industrial (PCI) District, at the meeting for which a public hearing had been advertised.
  • September 9, 2026: The Solicitor forwarded the draft ordinance, and the Board voted to advertise a public hearing.
  • July 28, 2026: The Planning Commission recommended the draft ordinance regulating data centers as a conditional use to the Board of Supervisors.
  • July 22, 2026: The Penns Valley Regional Planning Commission held a presentation and discussion on data centers.

Sources