Walker Township

Centre County, Pennsylvania. Status: Proposed Ordinance.

Skip the map

Walker Township's proposed ordinance would allow data centers only as a conditional use in the Light Industrial and Mineral Extraction districts under the district setback, coverage, and density rules, bar noise audible beyond the property line from 7 in the evening to 7 in the morning and audible 100 feet beyond it during the day, and require renewable energy equal to 100 percent of annual electricity use, closed-loop cooling with non-potable water for any water-cooled system, a water management plan with drought response, and annual energy and water reports. The ordinance has no number yet, and the township advertised it for consideration for adoption at the Board of Supervisors meeting on November 4, 2026.

Status
Proposed Ordinance
County
Centre County
Rating
Draft: 4 of 10 Core Protections addressed (Partial coverage), 0 at the strongest standard, 19 of 104 points
Where data centers are allowed
Proposed: conditional use in the Light Industrial and Mineral Extraction districts
Ordinance
None Adopted
Last verified
October 29, 2026

Key Milestones

  • November 4, 2026: The Board of Supervisors is scheduled to consider adopting the data center ordinance at its regular meeting, according to the township's legal notice.
  • October 20, 2026: The township secretary provided the legal notice and the full text of the data center ordinance planned for adoption by email.
  • October 19, 2026: The township asked that the request be submitted on a Right-to-Know form and said the drafted data center ordinance will be adopted at the November 4, 2026 Board of Supervisors meeting.
  • October 19, 2026: A Right-to-Know request for the current draft of the proposed data center zoning ordinance and any public hearing notice for it was emailed to the township.
  • July 1, 2026: The Supervisors voted 3 to 0 to proceed with the ordinance allowing data centers only in the Mineral Extraction and Light Industrial districts.