East Whiteland Township

Chester County, Pennsylvania. Status: Adopted Ordinance.

Skip the map

East Whiteland Township allows data centers only as a conditional use approved by the Board of Supervisors in the I Industrial District, at least 1,250 feet from homes, schools, and parks, with strict noise, water, and cooling limits. The rules are in Ordinance No. 385-2026, a municipal curative amendment the Board enacted on September 24, 2026, which does not apply to the previously approved Sentinel and Green Fig data center at the former Foote Mineral site.

Status
Adopted Ordinance
County
Chester County
Rating
9 of 10 Core Protections addressed (Broad coverage), 6 at the strongest standard, 66 of 104 points
Where data centers are allowed
Conditional use in the I Industrial District
Ordinance
No. 385-2026
Last verified
October 29, 2026

Key Milestones

  • October 23, 2026: The township denied two building permit applications for the project, B-2026-221 and B-2026-543.
  • October 20, 2026: The residents' group East Whiteland United sent a notice of intent to sue the township, its supervisors, Green Fig, and Sentinel over the project approvals and permits.
  • October 6, 2026: The township reported that it had received a fully executed water supply agreement between Aqua and Sentinel/Green Fig, a land development condition for building permits, and that no additional permits had been issued.
  • September 25, 2026: The developer withdrew its July footing and foundation permit applications for Buildings 1 and 2 and filed new ones.
  • September 24, 2026: After a public hearing, the Board unanimously adopted Ordinance No. 385-2026 regulating data centers.

Sources

See every Chester County municipality

Submit a Correction

Tell us what is out of date or incorrect, or send a new draft. A link to a supporting document, such as an ordinance or meeting minutes, helps us confirm the change. Corrections are reviewed within 30 days, and those tied to an upcoming hearing or vote are reviewed first.