West Goshen Township's revised proposed zoning ordinance would allow data centers only as a conditional use in the I Industrial district, with a 7-acre minimum lot, a 200-foot setback that rises to 1,000 feet next to residential uses or districts, a 60-foot height limit, noise limits of 55 dBA by day and 45 dBA at night at homes, Tier IV backup generators, and a required public sewer connection with a wastewater analysis. The Chester County Planning Commission's October 22, 2026 review letter found the revised ordinance consistent with county policy and recommended that the township address its comments before acting, and the Supervisors' November 5, 2026 agenda continued discussion of the update, including staff revisions to the backup generator and power generation provisions, with no hearing or adoption date set.

Status
Proposed Ordinance
County
Chester County
Rating
Draft: 7 of 10 Core Protections addressed (Broad coverage), 1 at the strongest standard, 36 of 104 points
Where data centers are allowed
Proposed: conditional use in the I Industrial district
Ordinance
None Adopted
Last verified
November 4, 2026

Key Milestones

  • October 30, 2026: The township posted the November 5, 2026 Supervisors agenda, which listed continued discussion of the zoning ordinance update with a staff memo on revised backup generator and power generation provisions.
  • October 22, 2026: The county Planning Commission issued its review letter on the revised zoning ordinance and map (ZO-09-26-19097 and ZM-09-26-19098), finding the update consistent with Landscapes3 and recommending that the township consider its comments before acting.
  • October 20, 2026: The Supervisors continued discussion of the zoning ordinance update, and the township manager reported that no follow-up county review letter had been received and that the version on the township website had been updated.
  • September 8, 2026: The township submitted revisions to the proposed zoning ordinance, made in response to the county Planning Commission comments, to the county Planning Commission for further review.
  • August 18, 2026: The Supervisors discussed the county comments on the data center provisions and were told the revised ordinance must return to the county for review.

Sources