Bigler Township
Clearfield County, Pennsylvania. Status: Adopted Ordinance.
Bigler Township, which has no zoning ordinance, regulates data centers township-wide through a standalone ordinance, with a 25-acre minimum lot, a 35-foot height limit that counts rooftop equipment, setbacks of 500 feet from property lines and 800 feet from homes and sensitive receptors, sound limits at the property line of 57 dBA on weekdays and 47 dBA at night and on weekends, a water feasibility study for any nonpublic water source, and decommissioning security of 110 percent of the estimated cost. The Supervisors enacted these standards as Ordinance No. 26-11 on November 2, 2026, and a draft county High Impact Development chapter that would add design and layout standards has not yet been advertised.
- Status
- Adopted Ordinance
- County
- Clearfield County
- Rating
- 7 of 10 Core Protections addressed (Broad coverage), 0 at the strongest standard, 44 of 104 points
- Where data centers are allowed
- Township-wide under a standalone data center ordinance (no zoning ordinance)
- Ordinance
- Ordinance No. 26-11, Adopted November 2, 2026
- Last verified
- November 14, 2026
Key Milestones
- November 13, 2026: The Township Secretary provided the text of the adopted ordinance by email.
- November 2, 2026: The Board of Supervisors enacted Ordinance No. 26-11, the Bigler Township Data Center Ordinance, according to the text of the ordinance.
- October 21, 2026: The county planning director said a newspaper reported that Bigler Township has advertised a data center ordinance.
- October 21, 2026: The county planning director said the County Commissioners approved moving the High Impact Development chapter into the public input phase, that it awaits the County Solicitor's review before it is advertised and released, that it will address high-impact uses through design and layout requirements only, and that a public hearing will be held before adoption, which the county aims to complete by the beginning of the new year.
- August 26, 2026: The draft High Impact Development chapter remained under county Planning Commission review.
Sources
- Clearfield County Planning Commission Agenda, April 22, 2026
- Clearfield County Planning Commission Agenda, August 26, 2026
- Municipalities Covered by County SALDO
- The Progress, June 23, 2026: Clearfield County considers new rules on data centers
- Clearfield County Planning Commission Agenda, May 28, 2025
- The Progress, October 23, 2026 (Clearfield County commissioners move forward with data center regulations)