Bigler Township

Clearfield County, Pennsylvania. Status: Adopted Ordinance.

Skip the map

Bigler Township, which has no zoning ordinance, regulates data centers township-wide through a standalone ordinance, with a 25-acre minimum lot, a 35-foot height limit that counts rooftop equipment, setbacks of 500 feet from property lines and 800 feet from homes and sensitive receptors, sound limits at the property line of 57 dBA on weekdays and 47 dBA at night and on weekends, a water feasibility study for any nonpublic water source, and decommissioning security of 110 percent of the estimated cost. The Supervisors enacted these standards as Ordinance No. 26-11 on November 2, 2026, and a draft county High Impact Development chapter that would add design and layout standards has not yet been advertised.

Status
Adopted Ordinance
County
Clearfield County
Rating
7 of 10 Core Protections addressed (Broad coverage), 0 at the strongest standard, 44 of 104 points
Where data centers are allowed
Township-wide under a standalone data center ordinance (no zoning ordinance)
Ordinance
Ordinance No. 26-11, Adopted November 2, 2026
Last verified
November 14, 2026

Key Milestones

  • November 13, 2026: The Township Secretary provided the text of the adopted ordinance by email.
  • November 2, 2026: The Board of Supervisors enacted Ordinance No. 26-11, the Bigler Township Data Center Ordinance, according to the text of the ordinance.
  • October 21, 2026: The county planning director said a newspaper reported that Bigler Township has advertised a data center ordinance.
  • October 21, 2026: The county planning director said the County Commissioners approved moving the High Impact Development chapter into the public input phase, that it awaits the County Solicitor's review before it is advertised and released, that it will address high-impact uses through design and layout requirements only, and that a public hearing will be held before adoption, which the county aims to complete by the beginning of the new year.
  • August 26, 2026: The draft High Impact Development chapter remained under county Planning Commission review.

Sources

See every Clearfield County municipality

Submit a Correction

Tell us what is out of date or incorrect, or send a new draft. A link to a supporting document, such as an ordinance or meeting minutes, helps us confirm the change. Corrections are reviewed within 30 days, and those tied to an upcoming hearing or vote are reviewed first.