Pine Township

Clearfield County, Pennsylvania. Status: Proposed Ordinance.

Skip the map

The draft county SALDO High Impact Development chapter would add review standards for data centers in Pine Township, which has no zoning ordinance (the county Planning Commission agenda of August 27, 2025 records its zoning as none). The county planning director said on October 21, 2026 that the chapter, which will set design and layout requirements only, awaits the County Solicitor's review before it is advertised and released, and that the county aims to have it in place by the beginning of the new year after a public hearing.

Status
Proposed Ordinance
County
Clearfield County
Where data centers are allowed
County SALDO High Impact Development draft; no zoning ordinance
Ordinance
None Adopted
Last verified
October 29, 2026

Key Milestones

  • October 28, 2026: The county Planning Commission agenda carried the draft High Impact Development chapter for the SALDO update as old business.
  • October 28, 2026: A county Planning Commission agenda listed the Wooster #2 subdivision in Pine Township with zoning recorded as none.
  • October 21, 2026: The county planning director said the County Commissioners approved moving the High Impact Development chapter into the public input phase, that it awaits the County Solicitor's review before it is advertised and released, that it will address high-impact uses through design and layout requirements only, and that a public hearing will be held before adoption, which the county aims to complete by the beginning of the new year.
  • October 13, 2026: The Clearfield County Commissioners agenda listed a High Impact Development update by the county planning director.
  • August 26, 2026: The draft High Impact Development chapter remained under county Planning Commission review.

Sources

See every Clearfield County municipality

Submit a Correction

Tell us what is out of date or incorrect, or send a new draft. A link to a supporting document, such as an ordinance or meeting minutes, helps us confirm the change. Corrections are reviewed within 30 days, and those tied to an upcoming hearing or vote are reviewed first.