Middle Paxton Township's draft Zoning Ordinance Update would allow data centers, including crypto mining and high-intensity compute-only centers, only as a conditional use in the Commercial-Industrial (C-I) District, on tracts of at least 20 acres with a 100,000-square-foot total building cap, a 35-foot height limit, a 300-foot setback from residential zones and sensitive receptors, and the township's general noise limits of 55 dBA by day and 45 dBA at night. The township posted the final revised draft, with pages dated September 17, 2026, on October 6, 2026 for the Planning Commission's final review; it has not been adopted, and no Board of Supervisors hearing date has been announced.

Status
Proposed Ordinance
County
Dauphin County
Rating
Draft: 6 of 10 Core Protections addressed (Partial coverage), 1 at the strongest standard, 34 of 104 points
Where data centers are allowed
Proposed: conditional use in the C-I District
Ordinance
None Adopted
Last verified
October 29, 2026

Key Milestones

  • October 21, 2026: The township manager said by email that the draft Zoning Ordinance is posted on the township website.
  • October 12, 2026: The Planning Commission agenda listed review and discussion of the final revised draft Zoning Ordinance Update and the summary of changes.
  • October 6, 2026: The township posted the final revised draft Zoning Ordinance Update and a summary of changes for public review before the Planning Commission's final review.
  • September 17, 2026: The working draft of the Zoning Ordinance Update, with data center standards in Section 1418, carries this date.
  • September 10, 2026: A resident told the Board of Supervisors of a petition asking for public forums on the final draft before adoption, and the manager reported meeting with the advisory group to finalize the draft.

Sources