Radnor Township is considering Ordinance 2026-24, which would allow data centers only as a conditional use approved by the Board of Commissioners in the PLO Planned Laboratory-Office District, with 200-foot setbacks from structures in residential, institutional, public land, and conservation districts, a 38-foot height limit, data processing space capped at 5 percent of building floor area, no more than a 3 dBA rise over a seven-day baseline sound level, air-based or closed-loop cooling, no groundwater or surface water withdrawals, Tier 4 Final generators tested only on weekdays from 10 a.m. to 4 p.m., required solar on roofs and parking areas, and $100,000 in water supply security returned 60 months after full production. The Board of Commissioners took up the ordinance for introduction on October 26, 2026 and advanced it for comment from the public and township boards, according to the agenda and The Philadelphia Inquirer, and no hearing date has been set and no data center is proposed in the township.

Status
Proposed Ordinance
County
Delaware County
Rating
Draft: 7 of 10 Core Protections addressed (Broad coverage), 2 at the strongest standard, 48 of 104 points
Where data centers are allowed
Proposed: conditional use in the PLO Planned Laboratory-Office District
Ordinance
None Adopted; Ordinance 2026-24 Introduced
Last verified
October 29, 2026

Key Milestones

  • October 26, 2026: The Board of Commissioners advanced a preliminary draft data center zoning amendment for public and board comment before a formal vote, according to The Philadelphia Inquirer.
  • October 26, 2026: The Board of Commissioners agenda listed Ordinance 2026-24, amending the zoning ordinance on conditional use standards and data center regulations, for introduction, with the draft ordinance attached.