Union Township
Huntingdon County, Pennsylvania. Status: Proposed Ordinance.
Union Township, which has no zoning ordinance, would regulate data centers township-wide under a draft Union Township Data Center Ordinance applied through land development review, with a 300-foot setback from the site boundary for buildings and major equipment, a 45-foot height limit, sound limits of 50 dBA by day and 45 dBA in the evening and at night at neighboring properties, annual compliance reports, and a closure plan without required financial security. The township provided this unnumbered draft on November 14, 2026, it follows a data center proposal along the Trough Creek Valley Pike, and it replaces a draft of October 22, 2026 that required a Data Center Permit after a public hearing and set a 35-foot height limit, limits of 45 and 40 dBA, and decommissioning security of 110 percent.
- Status
- Proposed Ordinance
- County
- Huntingdon County
- Rating
- Draft: 8 of 10 Core Protections addressed (Broad coverage), 1 at the strongest standard, 38 of 104 points
- Where data centers are allowed
- Proposed: township-wide site and operating standards applied through land development review (no zoning ordinance)
- Ordinance
- None Adopted
- Last verified
- November 14, 2026
Key Milestones
- November 14, 2026: The township provided its current draft of the data center ordinance and its earlier draft of October 22, 2026.
- November 2, 2026: The supervisors scheduled a special meeting on the data center proposal for 7:00 p.m. at the Trough Creek Fire Hall, according to The Daily News; no outcome has been posted.
- October 29, 2026: The Daily News reported that the supervisors were preparing a data center ordinance with a 300-foot setback, a 35-foot height limit, noise limits of 45 decibels by day and 40 decibels at night and on weekends, annual operating reports, and decommissioning security of 110 percent of estimated costs.
- October 24, 2026: The Save Trough Creek Valley group held a community meeting on how a zoning ordinance could be used to control the proposed data center, according to WJAC.
- October 22, 2026: The township prepared a first draft of the Union Township Data Center Ordinance, according to the dated copy the township provided.
Sources
- County table, Municipal Land Use Ordinances in Huntingdon County (July 2026)
- The Daily News, Data center proposed in Union Township (September 29, 2026)
- WTAJ, Huntingdon County residents raise concerns over proposed data center in Trough Creek Valley (October 6, 2026)
- The Daily News, Land owner addresses data center concerns (October 7, 2026)
- The Daily News, Residents seek data center answers (October 16, 2026)
- The Daily News, Data center concerns dominate meeting (October 21, 2026)