Throop Borough
Lackawanna County, Pennsylvania. Status: Adopted Ordinance.
Throop Borough allows data centers only as a conditional use, approved by Borough Council, in a Data Center Overlay (DC-O) District of about 351 acres, with a 125-acre minimum tract, 500-foot building setbacks, noise limits of 55 dBA by day and 45 dBA at night, and required closed-loop cooling. Borough Council adopted the rules as Ordinance No. 3 of 2026 on July 23, 2026; a further amendment updating the overlay regulations, which the county reviewed and returned on October 8, 2026, is pending with no Council hearing found, and the October 27, 2026 Council agenda referred to a validity appeal of the overlay amendment filed by Protectors of Water, Wildlife, Environment and Resources (POWER).
- Status
- Adopted Ordinance
- County
- Lackawanna County
- Rating
- 8 of 10 Core Protections addressed (Broad coverage), 0 at the strongest standard, 49 of 104 points
- Where data centers are allowed
- Conditional use in the Data Center Overlay (DC-O) District
- Ordinance
- No. 3 Of 2026
- Last verified
- October 29, 2026
Key Milestones
- October 27, 2026: The Council work session agenda listed a payment for planning services related to a validity appeal of the Data Center Overlay Amendment filed by Protectors of Water, Wildlife, Environment and Resources (POWER).
- October 8, 2026: The county Regional Planning Commission listed the borough's amendment updating the data center overlay regulations among its reviews, and its evaluation report noted that the referenced exhibits were not provided.
- September 28, 2026: County planning staff completed their review of the further amendment, according to the county Regional Planning Commission's list of data center amendments provided on October 22, 2026.
- September 24, 2026: The county Regional Planning Commission received the borough's further zoning amendment on data center regulations, according to the county Regional Planning Commission's list of data center amendments provided on October 22, 2026.
- September 1, 2026: The borough Planning Commission voted to approve further amendments to the data center overlay rules and send them to the county Planning Commission.