New Beaver Borough

Lawrence County, Pennsylvania. Status: Proposed Ordinance.

Skip the map

The October 13, 2026 draft would allow data centers, and energy generation systems serving them, only as conditional uses in the Industrial Park Overlay District, with an 80-foot height limit, 300-foot setbacks from all property lines that neighbors may waive, planted buffers of 100 to 300 feet near homes and sensitive receptors, noise limits of 55 dBA and 65 dBC by day and 45 dBA and 55 dBC at night with a 5 dBA cap over background, and closed-loop cooling unless an alternative uses no more water. The unnumbered draft was submitted to the Lawrence County Planning Department on October 13, 2026 and posted on the borough website on October 16, 2026, and it has not been adopted, with no hearing or vote date announced.

Status
Proposed Ordinance
County
Lawrence County
Rating
Draft: 9 of 10 Core Protections addressed (Broad coverage), 0 at the strongest standard, 49 of 104 points
Where data centers are allowed
Proposed: conditional use in the Industrial Park Overlay District
Ordinance
None Adopted
Last verified
October 31, 2026

Key Milestones

  • November 18, 2026: Borough Council has advertised a public hearing at 6:00 p.m. at the New Beaver Borough Volunteer Fire Department, 898 Wampum-New Galilee Road, on the zoning amendment regulating data centers and data center accessory uses, with consideration of adoption.
  • October 29, 2026: The borough posted a notice of public hearing and consideration to adopt the zoning amendment regulating data facilities and related accessory uses.
  • October 28, 2026: The New Castle News reported that the borough will look to adopt the data center ordinance soon and that the full draft is on the borough website.
  • October 19, 2026: The borough secretary emailed the proposed zoning amendment regulating data facilities and related accessory uses, dated October 13, 2026, and said hearing and meeting dates have not been advertised yet.
  • October 16, 2026: The borough posted the October 13, 2026 proposed data center zoning amendment on its website.

Sources

See every Lawrence County municipality

Submit a Correction

Tell us what is out of date or incorrect, or send a new draft. A link to a supporting document, such as an ordinance or meeting minutes, helps us confirm the change. Corrections are reviewed within 30 days, and those tied to an upcoming hearing or vote are reviewed first.