North Lebanon Township allows data centers only as a conditional use in the I-1 Industrial District, with a 20-acre or 40-acre minimum lot, a 1,000-foot setback from residential districts and sensitive receptors, a 100-foot landscape buffer, a 45-foot height limit, closed-loop cooling, and night noise limits of 40 to 45 dB at homes. The Board of Supervisors adopted the ordinance unanimously on November 16, 2026, according to LebTown. The standards described here come from the advertised final draft of Ordinance No. 3-2026, and the tracker has not yet seen the signed copy to confirm that the adopted text matches.

Status
Adopted Ordinance
County
Lebanon County
Rating
7 of 10 Core Protections addressed (Broad coverage), 4 at the strongest standard, 53 of 104 points
Where data centers are allowed
Conditional use in the I-1 Industrial District
Ordinance
No. 3-2026
Last verified
November 19, 2026

Key Milestones

  • November 16, 2026: The Board of Supervisors unanimously adopted the data center ordinance, according to LebTown. The signed Ordinance No. 3-2026 took effect on adoption.
  • October 21, 2026: The township manager provided the draft of Ordinance No. 3-2026 by email and reported that the Board of Supervisors authorized advertising it and scheduled the public hearing.
  • October 19, 2026: The township replied that drafts are exempt under the Right-to-Know Law until advertised, that the draft is on the October 19, 2026 Supervisors agenda to authorize advertisement and set a hearing date, and that the advertised version will be emailed.
  • September 21, 2026: Supervisors tabled advertising the draft while the solicitor works through Planning Commission revisions.
  • August 10, 2026: The Planning Commission received the draft, which was also under a 30-day county review.