Luzerne County, Pennsylvania. Status: Proposed Ordinance.

Skip the map

Hazle Township's November 5, 2026 Review Draft of its curative amendment would create an Energy and Technology Overlay (ETO) District, mapped by a list of parcels, where data centers are permitted by right, replacing the earlier draft's designated area of the I-1 district. The draft keeps setbacks of 1,250 feet from residential districts and sensitive receptors (reducible to 1,000 or 500 feet with lower noise), sets a 55 dBA Leq noise limit, a 60-foot height to the parapet, Tier 4 generators tested only on weekday daytime hours, and closed-loop, non-water, or reclaimed water cooling with public water and sewer, and raises decommissioning security to 120 percent while adding a public project website, independent review at the applicant's cost, and a 1:1 forest conservation rule. The text is an unadopted review draft of an amendment to Zoning Ordinance No. 2003-1-6-1, and no supervisors' hearing or vote date has been posted. At an October 29, 2026 special public meeting, many residents asked that data centers require a special exception instead, and the township solicitor said a curative amendment must be approved by December 7, 2026, according to the Times Leader.

Status
Proposed Ordinance
County
Luzerne County
Rating
Draft: 7 of 10 Core Protections addressed (Broad coverage), 2 at the strongest standard, 49 of 104 points
Where data centers are allowed
Proposed: permitted use in a parcel-mapped Energy and Technology Overlay District (review draft)
Ordinance
None Adopted
Last verified
November 10, 2026

Key Milestones

  • November 5, 2026: The township posted a revised November 5, 2026 Review Draft of the data center amendment that would permit data centers by right in a new parcel-mapped Energy and Technology Overlay District.
  • October 29, 2026: At a special public meeting at Hazleton Area High School, many residents asked that data centers require a special exception, and no vote was reported, according to the Times Leader.
  • October 26, 2026: The township's Discussion Draft #2 of the data center amendment, posted on its website, lists data centers as permitted uses in the I-1 district within a designated area.
  • October 20, 2026: The Planning Commission postponed discussion of the draft data center amendment to a special meeting because members needed more time to review it.
  • June 8, 2026: The supervisors unanimously declared the zoning ordinance invalid for failing to address data centers and began a 180-day pause while a curative amendment is prepared.