Jeddo Borough

Luzerne County, Pennsylvania. Status: Proposed Ordinance.

Skip the map

Jeddo Borough is under the Luzerne County Zoning Ordinance, and the county's proposed data center amendment would allow data centers only by special exception from the county Zoning Hearing Board, with edge and minor data centers in the GB, HB, LI, MI and HI districts and major and hyperscale data centers only in the MI and HI districts, setbacks from homes and other sensitive receptors of 1,250 feet for hyperscale and major and 650 feet for edge and minor data centers (reducible to 1,000 and 500 feet), a 60-foot height limit, closed-loop cooling, and property line noise limits of 55 dBA and 65 dBC. The county Planning Commission recommended an earlier version on May 14, 2026 and the revised draft (posted as of September 30, 2026) on October 8, 2026, and County Council listed it for discussion at its October 27, 2026 work session, after which the county Data Centers page stated that the Planning Commission will review an addition to the amendment proposed by County Council at its November 12, 2026 meeting, with no public hearing or vote date posted as of November 4, 2026.

Status
Proposed Ordinance
County
Luzerne County
Rating
Draft: 8 of 10 Core Protections addressed (Broad coverage), 1 at the strongest standard, 47 of 104 points
Where data centers are allowed
County zoning; proposed: special exception in the GB, HB, LI, MI and HI districts
Ordinance
None Adopted
Last verified
November 11, 2026

Key Milestones

  • November 12, 2026: The county Planning Commission is scheduled to review the addition to the data center amendment proposed by County Council at its 2:00 p.m. meeting.
  • November 4, 2026: The county Data Centers page stated that the county Planning Commission will review an addition to the amendment proposed by County Council at its November 12, 2026 meeting.
  • October 27, 2026: The County Council work session agenda listed discussion of the proposed county zoning amendment covering battery energy storage systems, data centers, data center accessory uses and energy generating facilities.
  • October 26, 2026: The Times Leader reported that County Council Chairman Jimmy Sabatino said the proposed data center zoning amendment would be discussed at two separate work sessions.
  • October 21, 2026: The county planning and zoning director said the draft data center amendment will be introduced at the County Council work session on October 27, 2026, and that public hearing and vote dates will be posted on the county website.