Newport Township

Luzerne County, Pennsylvania. Status: Adopted Ordinance.

Skip the map

Newport Township permits data centers by right only in its Mixed Use (MU) District under Section 517 of its 2026 zoning ordinance, with a 600-foot buffer from homes, schools, and parks (a 500-foot structure setback plus a 100-foot vegetative buffer), a 65 dBA noise limit, a full impact assessment for larger facilities, and a community benefit agreement. The current rules are in Ordinance No. 1 of 2026, the Zoning Ordinance of 2026, which the Board of Commissioners adopted on April 21, 2026.

Status
Adopted Ordinance
County
Luzerne County
Rating
7 of 10 Core Protections addressed (Broad coverage), 0 at the strongest standard, 28 of 104 points
Where data centers are allowed
Permitted by right in the Mixed Use (MU) District
Ordinance
No. 1 Of 2026
Last verified
October 29, 2026

Key Milestones

  • October 28, 2026: Fit Energy held a public information session at Greater Nanticoke Area High School, where its chief executive said the developer would next seek land development approval, according to the Times Leader and WNEP.
  • October 21, 2026: The county planning and zoning director confirmed that Newport Township left county zoning on April 22, 2026 and administers its own zoning.
  • October 6, 2026: Fit Energy announced a fuel cell power generation and data center campus on about 1,386 acres of former mining and quarry land in the township, which township documents describe as 15 data centers and three natural gas fuel cell stations totaling about 7.7 million square feet, according to PennLive and the Citizens' Voice.
  • October 5, 2026: Hundreds of residents attended a township board meeting to oppose the Fit Energy project, and the board said it had not yet received plans, according to the Times Leader.
  • September 24, 2026: The township posted a notice that zoning permits had been issued on August 10, 2026, that it had not yet received any development plans, and that the developer would hold a public meeting.