Muncy Creek Township

Lycoming County, Pennsylvania. Status: Adopted Ordinance.

Skip the map

Muncy Creek Township allows data centers and their accessory uses as a conditional use in the I-1 Light Industrial and I-2 Heavy Industrial Districts, with a 200-foot setback from residential districts and properties, a 60-foot height limit including roof equipment, a single 50 dBA noise limit at the property line, and required water, electric capacity, and emergency response documentation. The standards in § 27-439 were set by Ordinance No. 25-57, which the Board of Supervisors enacted on December 15, 2025 after a public hearing.

Status
Adopted Ordinance
County
Lycoming County
Rating
4 of 10 Core Protections addressed (Partial coverage), 0 at the strongest standard, 17 of 104 points
Where data centers are allowed
Conditional use in the I-1 and I-2 Industrial Districts
Ordinance
No. 25-57
Last verified
November 1, 2026

Key Milestones

  • October 19, 2026: The township secretary provided a signed copy of Ordinance No. 25-57 by email.
  • 2026-07: A supervisor stated that the township had received no data center application, after Muncy Township's solicitor said part of the Danko Holdings project lies in Muncy Creek Township.
  • December 15, 2025: After a hearing led by solicitor Wiley, the Supervisors approved Data Center Ordinance 25-57, which had been advertised twice and posted in the Lycoming County Law Library.
  • December 3, 2025: The Planning Commission discussed distances from homes, placement of data centers in the I1 and I2 districts, and conditional use hearings, and recommended adoption to the Supervisors.
  • November 17, 2025: The Supervisors voted to send Data Center Ordinance draft 25-57 to the township Planning Commission and Lycoming County Planning and to advertise a hearing for December 15, 2025.

Sources

See every Lycoming County municipality

Submit a Correction

Tell us what is out of date or incorrect, or send a new draft. A link to a supporting document, such as an ordinance or meeting minutes, helps us confirm the change. Corrections are reviewed within 30 days, and those tied to an upcoming hearing or vote are reviewed first.