The McKean County subdivision and land development ordinance's data center standards, adopted by the County Commissioners on September 8, 2026, govern data center site development in Keating Township because the township has no zoning or subdivision ordinance of its own, so zoning places no limits on where a data center may locate. Keating Township Ordinance No. 119, enacted in April 2026, also requires the applicant for any project with 10 or more acres of disturbance or total project area, including industrial and commercial facilities, to hold a public information meeting at least 30 days before applying for a permit and to mail notice to property owners within 2,500 feet.

Status
County Rules Apply
County
McKean County
Rating
County ordinance: 2 of 10 Core Protections addressed (Narrow coverage), 0 at the strongest standard, 13 of 104 points
Where data centers are allowed
County subdivision ordinance data center standards; township public information meeting ordinance for large projects; no zoning ordinance
Ordinance
County SALDO Amendment, signed September 8, 2026; Township Ordinance No. 119, April 2026
County rules
The September 8, 2026 McKean County amendment, which added data centers to the county subdivision and land development ordinance, applies here because Keating Township has no subdivision ordinance of its own and no zoning ordinance.
Last verified
October 30, 2026

Key Milestones

  • September 8, 2026: The McKean County Commissioners voted 3 to 0 to adopt the amendment to the county subdivision and land development ordinance (Ordinance No. 02 of 2016) regulating solar, wind, data center, and similar facilities.
  • August 31, 2026: The McKean County Commissioners held a public hearing on the subdivision ordinance amendment for solar, wind, and data center facilities.
  • 2026-04: The Keating Township Board of Supervisors enacted Ordinance No. 119, which requires a public information meeting and mailed notice to owners within 2,500 feet before permit applications for projects of 10 acres or more.