Hermitage City
Mercer County, Pennsylvania. Status: Adopted Ordinance.
Hermitage allows data centers only as a conditional use in its Light Industrial and Heavy Industrial districts, at least 1,500 feet from residential districts and 1,000 feet from streams, wetlands, and floodplains, with night noise limits of 45 dBA and 60 dBC, closed-loop cooling, Tier 4 generators, an emergency response plan, and a decommissioning bond of 110 percent. The Board of Commissioners enacted Ordinance No. 5-2026, which adds Section 321.500, on July 2, 2026, according to the signed copy the city provided, and the ordinance took effect seven days after enactment.
- Status
- Adopted Ordinance
- County
- Mercer County
- Rating
- 7 of 10 Core Protections addressed (Broad coverage), 2 at the strongest standard, 41 of 104 points
- Where data centers are allowed
- Conditional use in the LI and HI districts
- Ordinance
- No. 5-2026
- Last verified
- October 31, 2026
Key Milestones
- October 21, 2026: The city provided a signed copy of Ordinance No. 5-2026 and an approval letter by email.
- July 2, 2026: The Board of Commissioners held a public hearing and special meeting and enacted Ordinance No. 5-2026 on data centers.
- June 27, 2026: The Herald reported that the commissioners scheduled a special meeting and public hearing on the ordinance instead of waiting for their July 22 regular meeting.
- 2026-06: The Board of Commissioners unanimously introduced a data center ordinance limiting data centers to the Heavy and Light Industrial districts and sent it to the city Planning Commission for review.
- May 27, 2026: The Board of Commissioners adopted Ordinances 3-2026 and 4-2026 amending the zoning ordinance, whose updated text still defines a data center only as a centralized data repository and contains no data center standards.
Sources
- Hermitage Zoning Ordinance, updated May 27, 2026 (MCRPC copy)
- The Herald, City commissioners introduce data center ordinance
- The Herald, Special meeting Thursday for Hermitage data center ordinance (June 27, 2026)
- The Herald, Data center ordinance approved by Hermitage commissioners
- WFMJ, Hermitage commissioners tighten regulations for data centers (July 2, 2026)
- City of Hermitage data center zoning ordinance (posted copy, Section 321.500)