New Hanover Township

Montgomery County, Pennsylvania. Status: Proposed Ordinance.

Skip the map

New Hanover Township's zoning (Chapter 27 of the township code, codified on eCode360 through January 15, 2026) does not address data centers, based on a review of the chapter's contents, the township's 2026 new laws list, and 2026 Planning Commission minutes. General zoning rules still apply, and at the March 11, 2026 Planning Commission meeting the Commission was told that the County's position is that the township need not provide for data centers because Douglass Township, a partner in the regional plan, does. The Montgomery County Planning Commission reviewed the proposed data center ordinance in a letter dated November 4, 2026, and as of November 10, 2026 the county had not confirmed its adoption.

Status
Proposed Ordinance
County
Montgomery County
Where data centers are allowed
Not listed; a proposed data center ordinance is under county review
Ordinance
None Found; Draft Under Review
Last verified
November 10, 2026

Key Milestones

  • November 4, 2026: The Montgomery County Planning Commission issued its review letter on the proposed data center ordinance.
  • March 11, 2026: At the Planning Commission meeting, the Commission was told that the County's position is that New Hanover is not required to provide for data centers because Douglass Township does, and that the County has prepared a data center model ordinance.
  • February 11, 2026: At the Planning Commission meeting, a commissioner raised concerns about data centers, and the Commission was told that regional zoning offers protection from challenges when partner municipalities permit data centers.
  • January 15, 2026: The eCode360 codification of the township code was updated through this date.

Sources

See every Montgomery County municipality

Submit a Correction

Tell us what is out of date or incorrect, or send a new draft. A link to a supporting document, such as an ordinance or meeting minutes, helps us confirm the change. Corrections are reviewed within 30 days, and those tied to an upcoming hearing or vote are reviewed first.