Upper Moreland Township

Montgomery County, Pennsylvania. Status: Adopted Ordinance.

Skip the map

Upper Moreland Township allows a data center or data center campus only as a conditional use in the Limited Industrial District, with a 20-acre minimum lot (10 acres for data centers under 100,000 square feet), a 500-foot setback from all property lines and from residential uses and sensitive receptors, a 60-foot height limit, noise limits of 55 dBA by day and 45 dBA at night at residential property lines, and closed-loop cooling with evaporative systems prohibited. The standards were added by Ordinance No. 1780, which the Board of Commissioners enacted on October 5, 2026 after declaring on May 4, 2026 that its zoning ordinance was partly invalid for lacking any provision for data centers.

Status
Adopted Ordinance
County
Montgomery County
Rating
7 of 10 Core Protections addressed (Broad coverage), 4 at the strongest standard, 58 of 104 points
Where data centers are allowed
Conditional use in the Limited Industrial District
Ordinance
No. 1780
Last verified
November 1, 2026

Key Milestones

  • October 5, 2026: The Board of Commissioners enacted Ordinance No. 1780, allowing data centers by conditional use in the Limited Industrial District.
  • September 24, 2026: The Montgomery County Planning Commission logged the township's data center zoning ordinance amendment for county review.
  • September 21, 2026: The Community Development Committee reviewed the revised data center ordinance and recommended that the Board consider it on October 5, 2026.
  • August 3, 2026: The Board of Commissioners voted 5-0 to authorize advertisement of an ordinance amending the zoning code for data centers.
  • July 20, 2026: The Community Development Committee discussed a draft data center ordinance modeled on Montgomery County and Chester County Planning Commission guidance.