Mt. Carmel Township
Northumberland County, Pennsylvania. Status: Adopted Ordinance.
Mount Carmel Township allows data centers only as a conditional use approved by the Supervisors in the I-1A and S-2 districts, on lots of at least 20 acres with 40 percent building coverage, a 60 percent development area limit, a 60 foot height limit including rooftop equipment, no improvements within 1,500 feet of lots with homes or 600 feet of schools, places of worship, parks, and other sensitive receptors, a 100 foot vegetative screen, property line limits of 45 dBA and 60 dBC on weekday days and 40 dBA and 50 dBC at other times, weekday daytime generator testing, closed-loop or water-efficient cooling with monthly water reports, no access from township roads, disclosure of the operator and end user, and decommissioning security of 110 percent. The Supervisors passed the ordinance on October 21, 2026, and the posted copy leaves its number blank; the Supervisors also authorized a supplemental data center amendment, and the township has advertised a proposed data center registration and compliance ordinance, with no hearing date posted for either.
- Status
- Adopted Ordinance
- County
- Northumberland County
- Rating
- 9 of 10 Core Protections addressed (Broad coverage), 4 at the strongest standard, 57 of 104 points
- Where data centers are allowed
- Conditional use in the I-1A and S-2 districts
- Ordinance
- Adopted October 21, 2026 (Number Not Shown)
- Last verified
- November 2, 2026
Key Milestones
- October 27, 2026: The county Planning Commission agenda listed Blue Creek Investments preliminary land development plans for a 604,500 square foot North Data Center and a 616,500 square foot South Data Center in the township for local review.
- October 21, 2026: The Supervisors unanimously adopted the Mount Carmel Township Data Center Zoning Ordinance, a standalone zoning amendment allowing data centers only as a conditional use in the I-1A and S-2 districts, and authorized preparation of a supplemental data center amendment, according to the township home page and The News-Item.
- October 9, 2026: Blue Creek Investments submitted preliminary land development plans for two data centers, which the township found administratively incomplete and did not accept for filing, according to The News-Item.
- September 23, 2026: The township held a public hearing on the replacement amendment, with no action taken that night.
- September 22, 2026: The county Planning Commission listed the township zoning ordinance amendment among its notifications.
Sources
- Mount Carmel Township Data Center Zoning Ordinance, posted electronic copy passed October 21, 2026
- Mount Carmel Township home page (moratorium, hearing, drafts)
- Mount Carmel Township ordinances page
- Preliminary draft zoning amendment, August 12, 2026
- County Planning Commission minutes, April 28, 2026
- County Planning Commission agenda, September 22, 2026