Mt. Carbon Borough is governed by the Schuylkill County Zoning Ordinance, and the County Commissioners adopted Resolution No. 8-6-2026 on August 6, 2026, declaring the county zoning substantially invalid for data centers and committing to adopt a curative amendment within a 180-day period that ends February 2, 2027. At the October 14, 2026 county Planning Commission meeting, the consultant proposed allowing standard data centers by special exception in the Industrial-Commercial (I-C) District and hyperscale data centers by special exception in an overlay district whose location has not been set, and the Planning Commission listed the proposed amendments for possible action on November 4, 2026, ahead of a tentative December 9, 2026 hearing before the Commissioners.

Status
Proposed Ordinance
County
Schuylkill County
Where data centers are allowed
County zoning; data center curative amendment under county Planning Commission review
Ordinance
None Adopted
Last verified
November 11, 2026

Key Milestones

  • December 9, 2026: A public hearing before the Board of Commissioners on the county zoning amendments for data centers is tentatively scheduled, according to the November 4, 2026 county Planning Commission agenda package.
  • November 4, 2026: The county Planning Commission is scheduled to discuss and possibly act on recommendations to the Commissioners on the zoning amendments for data centers, battery storage, and solar energy systems, zoning map revisions, and subdivision ordinance amendments.
  • October 28, 2026: The county Planning Commission posted an agenda for a special meeting on October 28, 2026 to discuss the zoning amendments for data centers, battery storage, and ground-mounted solar.
  • October 14, 2026: The county Planning Commission heard its consultant propose standard data centers by special exception in the Industrial-Commercial District and hyperscale data centers by special exception in an overlay district whose location was not set, and took no formal action.
  • August 6, 2026: The Commissioners adopted Resolution No. 8-6-2026 declaring the county zoning substantially invalid for data centers and battery storage and committing to adopt curative amendments within 180 days.