Tamaqua Borough
Schuylkill County, Pennsylvania. Status: Adopted Ordinance.
Tamaqua Borough, together with the other Eastern Schuylkill Regional Planning members, allows data centers only as a conditional use in a new I Industrial District under its joint zoning ordinance, on lots of at least 30 acres, with noise limits of 75 dBA by day and 57 dBA at night and water and sound studies. Tamaqua Borough Council unanimously adopted Ordinance No. ESRP 2026-1 on October 6, 2026, after the joint public hearing, and Rush, Schuylkill, and Walker Townships adopted it the same evening, so it took effect under its own terms once the last member enacted it.
- Status
- Adopted Ordinance
- County
- Schuylkill County
- Rating
- 5 of 10 Core Protections addressed (Partial coverage), 0 at the strongest standard, 29 of 104 points
- Where data centers are allowed
- Conditional use in the new I Industrial District
- Ordinance
- No. ESRP 2026-1
- Last verified
- November 19, 2026
Key Milestones
- October 7, 2026: Rush Township posted the enacted text of Ordinance No. ESRP 2026-1, with its signed enactment page, on its website.
- October 6, 2026: Tamaqua Borough Council unanimously adopted Ordinance No. ESRP 2026-1 after the joint public hearing at Tamaqua Borough Hall, and Rush, Schuylkill, and Walker Townships also adopted it, according to the Times News.
- August 19, 2026: The Times News reported that the final draft went to the member planning commissions in July and would be advertised for an October 6, 2026 hearing.
- May 13, 2026: The Times News reported that the Eastern Schuylkill Regional Planning Commission had begun preparing data center and warehouse amendments, with an October 11, 2026 deadline for the 180-day period.
- April 25, 2026: The Times News reported that Tamaqua Borough Council unanimously approved a curative amendment recognizing that the joint zoning does not address data centers, warehouses, or short-term rentals.
Sources
- Ordinance No. ESRP 2026-1 (copy hosted by the tracker)
- Ordinance No. ESRP 2026-1 as enacted (posted by Rush Township)
- Rush Township, Ordinance No. ESRP 2026-1 posting, October 7, 2026
- Times News, Eastern Schuylkill planners approve data, warehouse zone (October 7, 2026)
- Tamaqua Borough Council minutes, September 15, 2026
- Draft Ordinance ESRP 2026-1 (posted by Schuylkill Township)