Harford Township

Susquehanna County, Pennsylvania. Status: County Rules Apply.

Skip the map

The county subdivision ordinance's data center standards apply in Harford Township because the township has no subdivision ordinance of its own (the county Planning Commission approves plans there), and the township has no zoning ordinance; the current county standards are in County Ordinance No. 2026-03, adopted April 8, 2026, which requires a 750 foot setback from residences, closed loop cooling, and noise limits of 67 dBA by day and 57 dBA at night. On August 11, 2026 the township supervisors voted to advertise their own data center ordinance (Ordinance No. 61) for possible adoption, but its text and any adoption vote have not been posted.

Status
County Rules Apply
County
Susquehanna County
Rating
County ordinance: 6 of 10 Core Protections addressed (Partial coverage), 0 at the strongest standard, 38 of 104 points
Where data centers are allowed
County SALDO data center standards (Section 713); township data center ordinance (Ordinance No. 61) advertised for possible adoption; no zoning ordinance
Ordinance
County Ordinance No. 2026-03
County rules
Susquehanna County Ordinance 2026-03, which added data center standards to the county subdivision and land development ordinance, applies here because Harford Township has no subdivision ordinance of its own and no zoning ordinance.
Last verified
October 31, 2026

Key Milestones

  • August 11, 2026: The supervisors voted to advertise Ordinance No. 60 (Solar Farms) and Ordinance No. 61 (Data Centers) for possible adoption.
  • July 28, 2026: The supervisors reported that the solar farm and data center ordinances remained tabled.
  • May 19, 2026: Two proposed ordinances setting development standards for solar farms and data centers were presented, and the supervisors tabled both for revisions.
  • April 8, 2026: Susquehanna County Commissioners adopted Ordinance 2026-03, Amending SALDO Regarding Data Centers, after a public hearing.
  • March 17, 2026: The Board of Supervisors discussed AI data centers and what regulations could be put in place.

Sources

See every Susquehanna County municipality

Submit a Correction

Tell us what is out of date or incorrect, or send a new draft. A link to a supporting document, such as an ordinance or meeting minutes, helps us confirm the change. Corrections are reviewed within 30 days, and those tied to an upcoming hearing or vote are reviewed first.