Charleston Township
Tioga County, Pennsylvania. Status: County Rules May Apply.
Charleston Township's 1975 zoning ordinance does not address data centers, so the Tioga County Data Center Ordinance may apply there, although its reach in a municipality with its own zoning is not confirmed, which requires approval of each data center by the County Commissioners, or by the county Planning Commission if the Commissioners delegate it, and sets no district limits or minimum lot size, but requires setbacks of 250 feet from property lines and roads and 1,000 feet from homes and other sensitive receptors, a 65-foot height limit, buffer yards of 100 to 300 feet near homes, closed-loop cooling, and a 57 dBA CNEL noise limit at property boundaries. The Board of Commissioners adopted the ordinance as Ordinance No. 2025-1, which the signed copy dates December 9, 2025, and amended and restated it by Ordinance No. 2026-3 on February 10, 2026; the county confirmed in October 2026 that it applies in every municipality without its own adopted data center ordinance, and the township's planned zoning update, which the Supervisors said in December 2025 would include data center provisions, would supersede it if adopted, though no draft is available yet.
- Status
- County Rules May Apply
- County
- Tioga County
- Rating
- County ordinance: 6 of 10 Core Protections addressed (Partial coverage), 1 at the strongest standard, 35 of 104 points
- Where data centers are allowed
- County data center ordinance (Ordinance No. 2026-3)
- Ordinance
- No. 2026-3 (Amending No. 2025-1)
- County rules
- Charleston Township has its own zoning ordinance, and Tioga County Ordinance No. 2026-3, a stand-alone county ordinance, states no authority that reaches a municipality with its own zoning ordinance, so it is uncertain whether the county rules apply here.
- Last verified
- November 1, 2026
Key Milestones
- October 22, 2026: County Administrative Director of Planning Kaye Aumick stated by email that the county Data Center Ordinance applies in every municipality that has not adopted its own data center ordinance, that a municipal ordinance supersedes it where one is adopted, that the Planning Commission has received no other municipal data center amendments, and that the county has not received any data center plans or applications.
- October 20, 2026: The township secretary said by email that no draft is available and that the draft will be posted on the township website once it is.
- October 19, 2026: County Administrative Director of Planning Kaye Aumick provided signed copies of Ordinance No. 2025-1 and Ordinance No. 2026-3 by email.
- July 6, 2026: The Supervisors corrected the minutes to state that the update will not exceed $15,000.
- June 15, 2026: The Supervisors voted to accept the Code Assessment Professionals quote of $10,000 to $15,000 to update the zoning and subdivision ordinances.
Sources