Deerfield Township

Tioga County, Pennsylvania. Status: County Rules Apply.

Skip the map

Deerfield Township is covered by the Tioga County Data Center Ordinance, which requires approval of each data center by the County Commissioners, or by the county Planning Commission if the Commissioners delegate it, and sets no district limits or minimum lot size, but requires setbacks of 250 feet from property lines and roads and 1,000 feet from homes and other sensitive receptors, a 65-foot height limit, buffer yards of 100 to 300 feet near homes, closed-loop cooling, and a 57 dBA CNEL noise limit at property boundaries. The Board of Commissioners adopted the ordinance as Ordinance No. 2025-1, which the signed copy dates December 9, 2025, and adopted Ordinance No. 2026-3 on February 10, 2026, which restates the ordinance with a larger home setback (up from 750 feet), a 250-foot property line setback (up from 200 feet), stricter height waivers, required closed-loop cooling, and full cutoff lighting.

Status
County Rules Apply
County
Tioga County
Rating
County ordinance: 6 of 10 Core Protections addressed (Partial coverage), 1 at the strongest standard, 35 of 104 points
Where data centers are allowed
County data center ordinance (Ordinance No. 2026-3)
Ordinance
No. 2026-3 (Amending No. 2025-1)
County rules
Tioga County Ordinance No. 2026-3, adopted February 10, 2026, is a stand-alone county ordinance that reaches data centers countywide by its terms, and it applies here because Deerfield Township has no zoning or subdivision ordinance of its own, although the county's authority to regulate data centers by a stand-alone ordinance has not been tested.
Last verified
November 1, 2026

Key Milestones

  • October 19, 2026: County Administrative Director of Planning Kaye Aumick provided signed copies of Ordinance No. 2025-1 and Ordinance No. 2026-3 by email.
  • April 17, 2026: The county Planning Director testified that the county ordinance applies where municipal regulations do not exist.
  • February 10, 2026: The Board of Commissioners adopted Ordinance No. 2026-3, which amends and restates the Data Center Ordinance with a 1,000-foot home setback, a 250-foot property line setback, required closed-loop cooling, and full cutoff lighting standards.
  • January 31, 2026: The public comment period on the county Data Center Ordinance closed.
  • December 9, 2025: The Board of Commissioners approved the Tioga County Data Center Ordinance for adoption and opened a 30-day comment period.