Shippen Township

Tioga County, Pennsylvania. Status: County Rules May Apply.

Skip the map

Shippen Township has its own zoning ordinance but no adopted data center ordinance, according to the county planning office, so the Tioga County Data Center Ordinance may apply there, although its reach in a municipality with its own zoning is not confirmed, which requires approval of each data center by the County Commissioners, or by the county Planning Commission if the Commissioners delegate it, and sets no district limits or minimum lot size, but requires setbacks of 250 feet from property lines and roads and 1,000 feet from homes and other sensitive receptors, a 65-foot height limit, buffer yards of 100 to 300 feet near homes, closed-loop cooling, and a 57 dBA CNEL noise limit at property boundaries. The Board of Commissioners adopted the ordinance as Ordinance No. 2025-1, which the signed copy dates December 9, 2025, and amended and restated it by Ordinance No. 2026-3 on February 10, 2026; the county confirmed in October 2026 that it applies in every municipality without its own adopted data center ordinance, and the county has received no township data center amendment for review.

Status
County Rules May Apply
County
Tioga County
Rating
County ordinance: 6 of 10 Core Protections addressed (Partial coverage), 1 at the strongest standard, 35 of 104 points
Where data centers are allowed
County data center ordinance (Ordinance No. 2026-3)
Ordinance
No. 2026-3 (Amending No. 2025-1)
County rules
Shippen Township has its own zoning ordinance, and Tioga County Ordinance No. 2026-3, a stand-alone county ordinance, states no authority that reaches a municipality with its own zoning ordinance, so it is uncertain whether the county rules apply here.
Last verified
November 1, 2026

Key Milestones

  • October 22, 2026: County Administrative Director of Planning Kaye Aumick stated by email that the county Data Center Ordinance applies in every municipality that has not adopted its own data center ordinance, that a municipal ordinance supersedes it where one is adopted, that the Planning Commission has received no other municipal data center amendments, and that the county has not received any data center plans or applications.
  • October 19, 2026: County Administrative Director of Planning Kaye Aumick provided signed copies of Ordinance No. 2025-1 and Ordinance No. 2026-3 by email.
  • April 17, 2026: The county Planning Director testified that the county ordinance applies where municipal regulations do not exist.
  • February 10, 2026: The Board of Commissioners adopted Ordinance No. 2026-3, which amends and restates the Data Center Ordinance with a 1,000-foot home setback, a 250-foot property line setback, required closed-loop cooling, and full cutoff lighting standards.
  • December 9, 2025: The Board of Commissioners approved the Tioga County Data Center Ordinance for adoption and opened a public comment period.

Sources

See every Tioga County municipality

Submit a Correction

Tell us what is out of date or incorrect, or send a new draft. A link to a supporting document, such as an ordinance or meeting minutes, helps us confirm the change. Corrections are reviewed within 30 days, and those tied to an upcoming hearing or vote are reviewed first.