A draft ordinance would allow data centers only as a conditional use in the Light Industrial District on lots of 30 acres or more, with buildings at least 1,500 feet from homes, schools, and residential districts, and it closely follows South Strabane Township's 2026 data center ordinance. The draft dated June 19, 2026 was presented at a public meeting on June 22, 2026, data center rules also appear in Section 400.21 of a draft township-wide zoning ordinance that the Planning Commission took comment on July 27, 2026, and the Supervisors' September 10, 2026 agenda listed no adoption vote or hearing on either draft.

Status
Proposed Ordinance
County
Washington County
Rating
Draft: 9 of 10 Core Protections addressed (Broad coverage), 5 at the strongest standard, 51 of 104 points
Where data centers are allowed
Proposed conditional use in the Light Industrial District
Ordinance
None Adopted
Last verified
November 1, 2026

Key Milestones

  • September 10, 2026: The Supervisors' agenda for this meeting listed no item on the data center ordinance or the draft zoning ordinance.
  • July 30, 2026: The Observer-Reporter reported that Amwell Township is using South Strabane Township's data center ordinance as a template.
  • July 27, 2026: The Planning Commission held a public meeting on a draft township-wide zoning ordinance that lists data centers as a conditional use in Section 400.21.
  • June 22, 2026: The township held a public meeting at Lone Pine Social Hall to take comment on the proposed data center amendment.
  • June 19, 2026: The township posted a revised draft data center ordinance dated June 19, 2026.