Fallowfield Township's Ordinance No. 249 makes data centers a conditional use in the I-1 and I-2 industrial districts and bars them from all residential, agricultural, and commercial districts, with a 500-foot setback from those districts and from sensitive receptors, a 60-foot height limit that includes rooftop equipment, and noise limits of 67 dBA by day and 57 dBA at night and on weekends at the property line, confirmed by preliminary, interim, and as-built sound studies. It also requires a water feasibility study when public water is not used, an emergency response plan accepted by the fire department, and facade articulation, and it treats on-site generation for normal operations as a separate use while requiring every data center to own a private self-supply power system. The Board of Supervisors adopted the ordinance on April 29, 2026, and this rating is based on the April 11, 2026 text of the ordinance because a signed copy has not been obtained.

Status
Adopted Ordinance
County
Washington County
Rating
5 of 10 Core Protections addressed (Partial coverage), 0 at the strongest standard, 29 of 104 points
Where data centers are allowed
Conditional use in the I-1 and I-2 industrial districts
Ordinance
No. 249
Last verified
November 10, 2026

Key Milestones

  • April 29, 2026: After a public hearing held just before its regular meeting, the Board of Supervisors adopted Ordinance No. 249, including the data center provisions, by a 3-0 roll call vote.
  • April 23, 2026: The township Planning Commission voted 5-0 at a special meeting to recommend that the Board adopt Ordinance No. 249.
  • April 11, 2026: The text of Ordinance No. 249 obtained by the tracker's maintainer, with the data center, rezoning, and solar provisions, is dated April 11, 2026.
  • March 25, 2026: The Board of Supervisors voted 3-0 to authorize advertising a public hearing on the zoning ordinance amendment, which the solicitor said included the data center article, a parcel rezoning, and solar rules.
  • March 13, 2026: At a special meeting, the Board of Supervisors voted 3-0 to authorize the solicitor to prepare a zoning ordinance revision creating a Data Center Ordinance.