Tunkhannock Township

Wyoming County, Pennsylvania. Status: County Rules Apply.

Skip the map

Tunkhannock Township is under the Wyoming County Subdivision and Land Development Ordinance, which reviews developments with data storage servers or other heat-generating equipment, large noise-generating equipment, or water use of 20,000 gallons per day or more as high-intensity nonresidential land developments and requires a sound impact study showing property line noise of no more than 55 dBA day and night, an approved electric service agreement, a water demand and cooling system narrative with a river basin commission permit at 20,000 gallons per day or more, sight-line renderings, fire protection improvements, and a heat-related site design narrative, with the applicant paying for county consultant review. The Wyoming County Board of Commissioners enacted the amendment on September 8, 2026, and it took effect on September 9, 2026, without the proposed 400-foot special setback for data centers, which the county Director of Community Planning wrote on October 21, 2026 was removed before adoption because setbacks in a subdivision ordinance might not be defensible under state law.

Status
County Rules Apply
County
Wyoming County
Rating
County ordinance: 4 of 10 Core Protections addressed (Partial coverage), 0 at the strongest standard, 24 of 104 points
Where data centers are allowed
County subdivision ordinance data center standards; no zoning ordinance
Ordinance
County SALDO Amendment, 2026
County rules
The September 8, 2026 Wyoming County amendment, which added standards for high-intensity nonresidential development, including data centers, to the county subdivision and land development ordinance, applies here because Tunkhannock Township has no subdivision ordinance of its own and no zoning ordinance.
Last verified
November 1, 2026

Key Milestones

  • October 21, 2026: The Wyoming County Director of Community Planning wrote that the adopted September 2026 subdivision ordinance amendment is posted and that the proposed 400-foot special setback for data centers was removed before adoption because setbacks in a subdivision ordinance might not be defensible under state law.
  • September 9, 2026: The county subdivision ordinance amendment, enacted September 8, 2026, took effect.
  • September 8, 2026: Wyoming County commissioners held a public hearing on the subdivision ordinance amendment.
  • September 8, 2026: The Wyoming County Board of Commissioners enacted the subdivision ordinance amendment for high-intensity nonresidential land developments, including data centers.
  • January 21, 2026: The county Planning Commission announced that staff would draft regulations for large developments, including data centers.

Sources

See every Wyoming County municipality

Submit a Correction

Tell us what is out of date or incorrect, or send a new draft. A link to a supporting document, such as an ordinance or meeting minutes, helps us confirm the change. Corrections are reviewed within 30 days, and those tied to an upcoming hearing or vote are reviewed first.